DC Virginia: the network room is done. This week the DC should be connected to the backbone :)
DC Virginia: the power supply for the phase 1 / roof upgrade / switch/ Room 0B / cooling system
DC Virginia: the power supply for the phase 1
DC Virginia: the roof upgrade is 40% done
switch on, switch off, switch on, it works
DC Virginia: testing UPS for the Network Room 0B… 15m17… not so bad
DC Virginia: testing UPS for the Network Room 0B… 15m17… not so bad
DC Virginia: deploying the cooling system
DC Virginia: the roof upgrade is 40% done
switch on, switch off, switch on, it works
DC Virginia: testing UPS for the Network Room 0B… 15m17… not so bad
DC Virginia: testing UPS for the Network Room 0B… 15m17… not so bad
DC Virginia: deploying the cooling system
DC Virginia: the rooms, 2000 servers each / rooms
DC Virginia (03/2017) / Elec Room 0B / first generator
DC Virginia (03/2017)
DC Virginia The fibers for the DWDM network from our DC in VA to 4 POP in USA:
1) Ashburn,VA
2) Newark,NJ
3) New York
4) Chicago,Il
DC Virginia: first room for the servers is ready. also the rooms for the energy
Читать дальше →
1) Ashburn,VA
2) Newark,NJ
3) New York
4) Chicago,Il
DC Virginia: first room for the servers is ready. also the rooms for the energy
Читать дальше →
DC Virginia (02/2017)
DC Virginia (02/2017)
DC Virginia USA (02/2017)
2 central rooms for the routers (02/2017)
DC Virginia USA: 2 central rooms for the routers that will forward the packets of the futur 80000 servers.